RUSH served as Design/Build Contractor of the Health First PET/CT Medical Group Cancer Center. The most challenging and rewarding part of this project focused on the design-build construction delivery method along with a very aggressive schedule that minimized the facility’s downtime. The design-build approach gave RUSH the ability to put together a select group of subcontractors, working in conjunction with the owner. This approach allowed for the facility to be back up and running in 6 weeks, rather than the usual 3 months required in a typical setting.

  • Project Location: Medical Cancer Center Melbourne, Fl
  • Facility Size: 2,500 sf
  • Construction Time: 1.5 months
  • Architect: Stephen L. Snow Architecture, LLC Cocoa, Fl
  • Engineer: TLC Engineering Orlando, Fl
  • Contract: Design/Build
  • Budget: $113,000.00
  • Owner: Health First Melbourne, Fl